Wednesday, July 23, 2008

21st and 22nd July Progress






Blockwork sub contractors turn up. They are good, quick and friendly - one couldn't really ask for more. Neil and Lewis continue joinery work internally.
Velfac send "Sprayrite" to fix damaged windows - they do a good job but you can see a difference between the powder coat and spray coat, not enough to condem the work but enough so that I have a little less enthusuiasm for Velfac windows.
Also Natralight send John and Russell to measure up the corner glazing - hopefully we can get them going soon.
Lastly our epdm flat roof membrane arrived along with the witches hat. Pictures to follow.